Will it be ready in time? The delay status
Qivo estimates an unfinished task's finish week from its plan, remaining hours and owner's workload. Delay tracking highlights two warnings:
- Behind plan, in yellow. The projected finish is after the planned end, without a missed or projected-to-miss due date.
- Late, in red. The projected finish is after the due week, or the exact due date has already passed.
On track has no warning color. While the due date has not passed, finishing in the due week is not classed as Late, though the hover text of its roadmap due-date marker says that the schedule is tight. Done tasks have no delay verdict. Tasks without a plan or due date also have no verdict. A task with only a due date needs an owner and remaining hours for a projection; without them, it gets a warning only once overdue.
How the projection works#
Qivo projects one owner's planned unfinished tasks together, week by week, against the owner's plannable hours (Planning hours). Each Remaining save records when you measured it, and a task's remaining hours count from that week. A task takes part from that week or its planned start, whichever is later.
In each week, every task that has started asks for its remaining hours divided by the weeks left in its plan, that week included. A task whose plan has ended asks for all its remaining hours.
- When the asks fit in the owner's weekly hours, every task gets what it asks for. A task that gets its ask every week finishes in its planned end week.
- When they do not fit, the week is overbooked, and every task gets the same share of its ask. The hours a task did not get stay as its remaining hours and move to the next week, where it asks again.
A task's projected finish is the first week in which it gets all its remaining hours, which only a week that is not overbooked can give. So no task finishes in an overbooked week, however few hours it has left. For example, a person with 32 hours a week has three tasks of 32 hours each, all planned for this week only. Each gets a third of the week, and all three are projected to finish in the third week, Behind plan. A task squeezed in one week asks for more in the weeks left in its plan, so it can still finish on time when those weeks have room.
A task with remaining hours but no plan, and a paused task, ask for nothing and take no hours from the planned tasks. Each one is fitted on its own into the hours the planned tasks leave free, so such tasks take no hours from each other either. For example, two such tasks of 32 hours each, with 32 free hours in the coming week, are both projected to finish in that week, though together they need two weeks. Read their finish weeks one task at a time, not as a plan that fits together.
The projection counts the owner's other open work as you may see it. Organization admins and users receive organization-wide commitments, with hidden-project hours kept anonymous. Viewers and guests receive only work from visible projects and tasks they own (Project access).
The projection assumes progress since the measurement, so an estimate's age alone does not add more work. Saving another estimate starts the calculation from the new measurement. An unfinished task's projected finish cannot be earlier than the current week. The projection follows an owner through at most 520 overbooked weeks, ten years. A task it has not finished by then is projected to finish in the week after them, or at its planned end if that is later, and a task without a plan or a paused one gets no free hours from that week on.
The owner is the assignee, or the reviewer while the task is In Review with one. Without an owner, remaining hours or positive weekly capacity, the projection uses the planned end, or the current week if that end has passed. Agents have no weekly capacity limit, so every ask fits. An agent's task with remaining hours is projected to finish at its planned end, and competing workload does not extend it. Without a plan, or while paused, it is projected to finish in the current week, or at its planned start if that is later, as with 0 Remaining below.
0 Remaining means no work left, while an empty field means no estimate. With an owner and capacity, zero projects completion in the current week or the planned start week if later. A passed due date still makes the task Late, and a passed planned end can still make it Behind plan.
A group's planned end is the latest end of its scheduled subtasks. Groups use that end and their due date, not their saved status or a separate estimate. A saved Done status cannot hide a missed deadline while descendant work is unfinished. Once all descendant work is Done, the group has no delay verdict.
When Qivo cannot read all of a group's subtasks, such as for a very large group, the group can show only Late, and only when its due date has passed or the subtasks it read already end after the due week. Otherwise it has no verdict, because the plan it read cannot show whether the group is on track. For the same reason, when that plan ends before the due date, the hover text of its Roadmap due line says that Qivo could not read all of its subtasks.
Where you see it#
- Roadmap colors a bar yellow or red from the today line on, and its unplanned marker and edge badges with it. A bar whose plan ended before the current week runs on to the end of the current week. Projected delay, on by default, adds diagonal stripes to the end of the projected finish week (Scheduling by hand). A due-date line is one neutral mark; hover it for its explanation. The Roadmap reads the owner's other work from the server too, and where that work cannot be read, a bar turns gray with a dashed outline and its hover text, like its due-date line's, says Delay unknown.
- Board shows Behind plan or Late above the card. The due-date tooltip also explains projected misses. Qivo reads the owner's other work from the server for the Board's cards, so their delay shows without loading every task; where that work cannot be read, the card says Delay unknown. A task you create shows on the Board at once, and its card takes its delay from the server like any other.
- Task window shows Behind plan or Late beside Due. Hover for the projected finish week. A missed or projected-to-miss deadline outlines Due in red. Qivo reads the owner's other work from the server, as for the task's Board card, and the window shows the same verdict as its card, also for a task you just created. The window shows nothing while that work is on its way, and says Delay unknown only where it cannot be read. A passed due date shows Late. A task with subtasks takes its delay from its subtasks' dates, not from anyone's other work, so it says Delay unknown only while some of those dates have not loaded. In the task window, those are the dates of its subtasks, which the window reads with the task. Where it cannot read them all, it takes the dates from the task's card or row in an open view that shows it, and follows as they change. Without one, as when that view is hidden behind another page, it says Delay unknown, or Overdue once the due date has passed.
- Team sync shows the same banner as a Board card on its rows, Delay unknown included, judged on the server with each owner's other work. Where Qivo could not read someone's other work, the team summary's Projected to miss and Behind plan counts read unknown, never 0 (Team sync).
- Overview lists projected misses under Projected to miss and tasks behind plan under Behind plan in a project's Needs attention, and counts Late and Behind plan for each sub-project, all worked out on the server with each owner's other work. Where Qivo could not read that work, the Projected to miss and Behind plan tabs show a dash for their count and say that they may leave tasks out, and a sub-project's Late and Behind plan read unknown, never 0 (Needs attention). In My view such a row of Your work says Delay unknown, and the counts of Your projects read unknown too (My view's Overview).
- REST and MCP task results carry the same verdict as
delay, judged on today's date in UTC. A task's verdict says it is unavailable when Qivo cannot read the owner's other open work in one request. A row of a task list can also say unavailable when Qivo did not read the owner's other work for that page. A page reads that work within a fixed share of what it may read, so the rows of a person with very much open work can say unavailable on every page. For a guest or Viewer, Qivo reads it for only the first person on a page who needs it. Reading the task itself gives its verdict. See Automation & AI.
Turning it on and off#
Change Delay tracking in Project settings. It defaults to on. Turning it off removes delay colors and projected stripes; the hover text of roadmap due-date markers still compares the planned end with the due date.
Review time#
Moving a task into In Review sets Remaining to its review time, 2 hours by default, and records a new measurement even if the number is unchanged. With a reviewer assigned, these hours count toward the reviewer's workload. Leaving In Review keeps the remaining value. Update it if the next work needs a different estimate.
People with Lead access can set Review time in Project settings, from 0 to 999 hours. Sub-projects follow the project's value unless they set an override. Clear the override to follow the project again. Changes apply to future moves into In Review; tasks already there keep their estimates.