The Roadmap
The Roadmap shows scheduled tasks as bars on a weekly timeline, for one project, one sub-project or My view. In a project, tasks sit under their sub-projects. My view groups your own tasks by project, then sub-project. An address that once named all projects opens as the Roadmap's own address does (All projects). Undated tasks appear below the scheduled tasks with an unplanned marker and their due date, if set. Click one to open it and set its plan. Tasks with subtasks take their dates from them instead.
Project and sub-project headings show their unfinished tasks' total remaining hours and stay visible while you scroll their rows. While Qivo is still counting those hours, a heading reads Counting…, and where it could not count them within its limits, a muted unknown. Neither means zero hours. Use a heading's arrow to collapse it. The double chevron in the Task header collapses or expands all groups, including groups inside collapsed projects. Filters hide groups with no matching tasks; clearing a filter restores their previous collapsed state.
Backlog tasks are hidden, even when scheduled. Done tasks are hidden too while Hide Done in Roadmap is on (below). With it off, Done tasks appear only when their planned period overlaps the visible window, including its first and last weeks. Undated Done tasks are hidden. To Do, In Progress and In Review tasks outside the window remain available through edge badges or unplanned rows. Filters cannot bring hidden Backlog or Done tasks back. A task with subtasks follows its subtasks instead of its own hidden status: it is never hidden as Backlog, and it counts as Done only when all its subtask work is Done. These rules also apply to the phone's landscape timeline and Task schedule, which uses the current roadmap window.
Hide Done in Roadmap, under Settings → Your preferences → Appearance, is on until you turn it off. While it is on, Done tasks take no row, so they take no space between your unfinished work. That includes a task with subtasks once all its subtask work is Done, and a Done subtask under an unfinished parent. Project and sub-project headings stay, with their unfinished tasks' remaining hours. Dependency arrows to and from a hidden task are not drawn. Team utilization still counts the people who own the hidden tasks, so it shows the same figures with the setting on and off. Where every task the Roadmap would show is Done, it says Done tasks are hidden and where to turn the setting off, with Clear filters while a filter is on. Plan on roadmap or Show on roadmap for a hidden Done task says so instead of showing it, and the Roadmap keeps its window where it was. A Team sync jump to a task that has become Done since its row was drawn says so too, where the Roadmap can tell that the task is Done. A planning session ends when its task becomes Done. The setting follows your account across organizations and devices, and applies in every project, in My view and on the phone.
The Roadmap shows at most 1,000 tasks at a time, counting each task with subtasks and each subtask, across the project or sub-project with its filters and window, or My view. Done tasks that Hide Done in Roadmap hides count too. A selection past that, or one Qivo could not read within the Roadmap's limits, shows no tasks and says so instead of showing part of it. Choose one of the sub-projects it offers or narrow your filters, such as Priority or the text filter. A shorter window rarely helps, as unfinished tasks show whatever their dates and only Done tasks follow the window (Limits). When you move the window or type more of the text filter, the Roadmap keeps its timeline until the new answer arrives; another filter shows Loading tasks… until its tasks arrive.
A window you control#
The starting range is two weeks before today through six weeks after today. Use the controls on the timeline to change it:
- The arrows before and after the week header move the view by 20% of its span.
- The calendar button in the Task header offers a month, two months, a quarter, half a year or a year. Custom range… lets you set each end separately as Relative weeks, which move with today, or an Exact date. The Roadmap shows at most 260 weeks, about five years. Custom range… refuses a wider range and says so. A range that grows wider later, such as an exact start with a relative end as the weeks pass, shows its first 260 weeks, and the header says First 260 of N weeks.
- Save this as my default saves the current range for your account. The Roadmap opens on it, and Default window or the reset button returns to it. The reset button appears only when the view differs from your default.
- At your saved default, Forget my default restores the standard range.
Arrow badges at either edge describe tasks whose planned periods extend beyond the window. A badge joined to a bar means the task continues beyond that edge. A detached badge means the whole task lies outside the window. It is filled for an adjacent week and outlined when at least one full week separates the task from the window.
Hover or keyboard-focus a badge to read its endpoint week. Click it to bring that endpoint into view without changing the number of visible weeks. Ended W37 describes the plan, not whether the task is Done. Connected and adjacent badges match the bar where it meets the window's edge: gray for planned time before the current week, otherwise the bar's color. More distant badges are outlined, neutral unless delay tracking marks them yellow or red (Delay status). Badges count planned weeks only. A run-on or projected finish (below) that reaches past the window is cut at its edge.
Weeks that match your calendar#
Week numbers and first-workday dates follow your organization's calendar settings (Organization settings). Month boundaries have solid gridlines; other weeks use dashed lines. Narrow columns shorten the labels.
Plans use whole weeks. Bars snap to weeks, while due-date markers retain exact dates.
The one-milestone-a-week rule counts each project's weeks in the calendar of the organization that owns the project. If you work as a guest in another organization whose weeks start on another day than your own, the Roadmap still shows your organization's weeks. A week that looks free there can then hold one of the project's milestones in its owner's calendar, and Qivo refuses a milestone moved into it, naming that week in the owner's dates.
Scheduling by hand#
With edit access, drag a bar to move it or drag either edge to resize it. Release to save. Click a bar or task name to open its details. Read-only bars and the bars of tasks with subtasks open but cannot move or resize.
In a Plan on roadmap session with Auto-fit end to workload on, a drop sets the end for you, at a week by which the delay projection finishes the task, so it is not Behind plan. Qivo looks for the earliest such week, and for an owner with a lot of open work it can settle on a later one. When Qivo finds no end within its limits, the end stays where you dropped it and the planning panel says so, and a Done task always moves as you drop it (Plan on roadmap). Placing a task in weeks that are already full can still make the owner's other tasks in those weeks read Behind plan. With All projects chosen, Team utilization shows the hours planned in each week in the projects you can see. The delay projection also counts unfinished hours that move on from earlier weeks, so a week can be full for the projection while Team utilization shows it below 100%.
Click the portrait beside a task to change or clear its assignee. Its list shows the people who can take the task, 25 at a time with a search and Load more, as the task window's Assignee does (The details column). For a task In Review with a reviewer, the portrait and picker show the reviewer instead.
Bars fill the whole planned period; their length does not show completion. The part of an unfinished task's bar before the today line is a quiet gray. From the today line on, a bar has the color of its status on the Board: To Do a stronger gray, In Progress blue and In Review violet. A task with subtasks has no status of its own, so its bar is In Progress blue once one of its subtasks has started, and To Do gray before. Where the project tracks delay, a Behind plan task is yellow and a Late task red from the today line on, whatever its status (Delay status). The hover text names the status and the delay. A bar is gray with a dashed outline, and its hover text says Delay unknown, when Qivo could not read its owner's workload to judge it.
An unfinished task whose plan ended before the current week runs on from its planned end to the end of the current week, in its yellow or red. Where the project does not track delay, the run-on is a faint dashed stretch in the status color. The run-on is not part of the plan: it follows the bar, a drag on it moves nothing, and the plan still ends where the gray ends.
Projected delay in the toolbar draws diagonal stripes in the same yellow or red from the end of a Behind plan or Late bar, or its run-on, to the end of the task's projected finish week, which the hover text names. The stripes assume that in an overbooked week each of the owner's tasks gets the same share of the hours it asks for, the rest moving to later weeks, and that remaining hours count from the week they were last updated (How the projection works). With 16 hours in a week and asks of 24 and 8 hours, the tasks get 12 and 4. It is on by default. Switching it off hides the stripes and the projected finish week in the hover text, and nothing else, for your account, in every project, in My view and on the phone's landscape timeline.
With Hide Done in Roadmap off, Done bars are dim gray, including groups whose descendant work is all Done. A finished bar in the past never has a run-on, which tells it apart from unfinished work. A paused task's planned bar keeps its color under diagonal lines and, where it is wide enough, shows a pause sign at its start. A run-on and stripes after it have no lines. Its connected and adjacent edge badges get the lines too.
A task with subtasks takes its dates from them. Its bar runs from the earliest start to the latest end of its active scheduled subtasks, at any depth and in any status. To change the bar, move its subtasks. A task with subtasks but none scheduled shows as unplanned. While you drag a subtask, its parent's bar follows it.
Milestones appear as violet diamonds. In a project or sub-project they sit in the header under the week numbers, and each one's dashed line runs down through every row. In My view each milestone sits on its own project's row with its name, and its dashed line runs through that project's rows only, so two projects' milestones of the same week sit on their two rows. Drag one to move it or click it to open the Milestones window, which reads that milestone from the server as an Overview row does (Overview milestones). In a project, the toolbar's Milestone button creates one. A diamond of a project Qivo is still loading can be opened but not dragged until it loads, and a Viewer's never moves. A project has at most one milestone a week, so a diamond dropped on a week that already has one of the project's milestones goes back, and Qivo names the milestone there. Each name stays on one line and runs from its diamond to the next milestone in its row, or to the left near the end of the timeline. In the header, milestones of the same week, or close together, take rows of their own, and the header grows when one week holds more than two milestones or the names need more room, as far as the screen leaves room for your tasks. Where a name is still cut short, hover the milestone or move to it with Tab to read it in full, and press Enter to open it. When one week holds more milestones than the header shows, scroll the milestone rows to reach the others. Beside the rows, +N more says how many milestones are out of sight above or below them. A project's row in My view holds two rows of milestones and cuts names short where they meet. The Roadmap loads the milestones of the weeks it shows, and moving or resizing the window loads those of the new weeks; meanwhile the milestones of the weeks both windows share stay. A line under the toolbar says when the milestones are still loading, could not load (Retry loads them again), are not all shown because the window held more than Qivo reads at once (it says from which day, and that a shorter window, or in My view opening a project, can help), or belong to more projects than the app reads at once (Limits). Unlike for tasks, a shorter window reads fewer milestones. On a phone, the Roadmap's agenda lists milestones as the Overview does (Overview milestones), not by the timeline's weeks. When a scope has nothing to schedule, for example a project without sub-projects or My view with nothing assigned to you, the Roadmap says why. In a project or sub-project, and in My view, the timeline stays behind that note with its window controls, and in a project with the milestones of its window. My view with no project shows only its note.
Undo this Roadmap visit's changes#
Undo reverses your latest planning change, then earlier changes from the same Roadmap visit. Changes save immediately, including restored values. One Auto-move action counts as one undo step for all the tasks it moves.
History includes task dates and milestone additions, edits and deletions. Display preferences, filters and the visible date window are unaffected.
Changing projects or filters within Roadmap keeps history. On a phone, switching between the agenda and timeline also keeps it; Undo sits below Timeline & team, beside Auto-move. Opening a task to read it keeps history, but saving a change there or changing an owner through a roadmap portrait clears history and stops recording until you leave Roadmap and return.
Leaving Roadmap or reloading clears history without reverting saved changes. History expires after 24 hours and holds up to 1,000 steps per visit. If an intervening change conflicts with an undo, Qivo refuses the entire restoration and clears history until your next visit. A milestone that took a week since the change you undo counts as such a change, when the undo would bring a milestone of the same project back into that week. Followers of the tasks a change or an undo touches get the update in their inbox a few seconds after it saves. A change that touches too many tasks to save in one go is refused, and nothing changes. An undo that large is refused the same way, and history stays.
Dependencies you can see and safely fix#
Blocks links appear as finish-to-start arrows between two bars on the timeline. A gray arrow means the blocker ends before the blocked task starts. A red arrow means it ends in or after the blocked task's start week, and the blocked task's bar gets a red ring. Arrows update while you drag. A task you have just scheduled shows its arrows once its dates are saved. When Qivo cannot read the selection's links within the Roadmap's limits, no arrow shows, and a line above the timeline says why. A link to or from a Done task that Hide Done in Roadmap hides has no arrow.
Auto-move shifts blocked tasks to start after their blockers, including chains of dependent tasks. It works on the tasks linked to this Roadmap's tasks, here or in other projects, and leaves chains with no task on this Roadmap alone. It moves a task with subtasks by moving its subtasks. It never moves Done or Backlog tasks, or tasks you cannot edit, though they still count as blockers. A conflict stays red when fixing it would mean moving one of them. Cycles remain unresolved with red arrows, so you must remove or change those links. When the selection's dependency chains are too long to read at once, Auto-move is unavailable and says so, and the arrows still show. It also waits until your changes, on the Roadmap or elsewhere, are saved. Auto-move saves its moves as one undo step, so while this visit's undo history is cleared it is unavailable too: leave Roadmap and return to use it again. It says how many tasks it moved once they are saved, and if the save is refused it says why and no task moves.
Refresh remaining hours before you plan#
Workload figures and delay projections use each task's Remaining hours. Update them in the task window's details (The task window), or one person at a time in Team sync (Team sync). Team sync lists your own organization's projects, so if you only have guest access, or the project is shared from another organization, use the task window. Each saved Remaining starts a new measurement for delay projections (Delay projections).