Planning against real capacity
Plan on roadmap#
Plan on roadmap opens the timeline and highlights the task, on the Roadmap of the project, sub-project or My view you are on when that holds the task, else on the task's top-level project. The task stays on the timeline for the session whatever the filters, and the Roadmap moves its window to the task first if needed. Unscheduled tasks receive a starter bar. A Backlog task must first move to another status; trying to plan it leaves its dates unchanged. Done tasks that have dates can still be moved on the Roadmap while Hide Done in Roadmap is off. While it is on, the Roadmap says the task is Done and hidden, and where to turn the setting off, and starts no session. A Done task without dates cannot be planned there, so its button is off and says why. When the task cannot show on that Roadmap, for example because the project is past the Roadmap's 1,000-task limit, Qivo says why and starts no session. If the task leaves the Roadmap during the session, for example because someone moved it to another sub-project that your filters hide, the session ends and its dates stay as they were saved. Planning another task while a session is open moves the session to that task once the Roadmap shows it; the first task's dates stay as they were saved.
A task with subtasks takes its dates from them, so its button reads Show on roadmap. It opens the timeline and finds the task's bar or unplanned row without starting a planning session or changing any dates. Other filters clear so the task stays visible; Focus is kept. Plan its subtasks instead.
The planning panel offers:
- Auto-fit end to workload, on by default for tasks without subtasks that are not Done, with an owner and positive Remaining hours. After each drag, Qivo looks for the earliest week by which the delay projection finishes the task and sets the end there, with the owner's other tasks sharing their weekly hours (How the projection works). An end Qivo sets this way is not Behind plan, though it is Late when it is after the task's due week. The end is no earlier than the start, the estimate measurement week or the current week. A paused task asks for no hours, so its end is where the hours the other tasks leave free cover it. Qivo looks for an end up to 520 weeks, ten years, after the first, and for an owner with a lot of open work it can stop looking sooner. It then tries the week in which the hours the other tasks leave free cover the task, and uses it if the projection finishes the task by then, though an earlier week may work too. When Qivo finds no end, the end stays as it is, and the panel says Auto-fit found no end within its limits, so the end stays as it is. The task can then read Behind plan. Placing a task in weeks that are already full can still make the owner's other tasks in those weeks read Behind plan. With All projects chosen, Team utilization shows the hours planned in each week in the projects you can see. The delay projection also counts unfinished hours that move on from earlier weeks, so a week can be full for the projection while Team utilization shows it below 100%. Auto-fit uses the reviewer while a task is In Review with one and follows ownership changes during the session. While Qivo loads the owner's details the panel says Loading the owner's hours…, and the first fit of an unscheduled task waits for their weekly hours. If Qivo could not read their hours, it says Capacity unknown, so auto-fit is off. A Done task's dates record when the work happened, so a drag moves or resizes it as you drop it, and the panel says Done, so auto-fit is off.
- The owner's committed hours by project, excluding paused work. Hidden projects appear as anonymous Other projects hours where your role allows it (Delay projections). The free-hours summary uses that person's plannable week. These figures update while you plan: your own changes count at once, and changes others make to the owner's work show as they save. As a guest or organization Viewer looking at someone else's work, the panel says Counts only projects you can see.
- Confirm to keep the dates or Cancel to restore the original dates, including an unscheduled state.
Agents have no weekly capacity limit. Auto-fit ends in the start week, the measurement week or the current week, whichever is latest, and shows No weekly capacity limit for auto-fit. When Qivo cannot read the owner's workload, for example when they hold more open work than it reads at once, the panel shows Workload is unavailable and auto-fit pauses until Qivo can read it again. That applies to agents too.
The Team strip#
Team utilization sits below the Roadmap on the same weekly grid, with the timeline's week lines. People and agents appear alphabetically. Each person's cells show their scheduled load as a percentage of their own plannable hours, over a thin line that fills up to 100%. A week without load stays blank, and a week whose load is too small to show as a figure reads 0% over an empty line, or 0 h in a row that shows hours. While Qivo reads a person's workload their cells show …, and where it could not read it, for example past the bounds of one read, a cell says unknown, never blank. As a guest or organization Viewer, Qivo reads the workload of the 50 people with the most tasks on the Roadmap, and shows the others as unknown. Their weekly capacity appears beside their name. New people start with the organization default, initially 32 hours (Planning hours). While Qivo loads a person's details their row says Loading…, and a person whose weekly hours Qivo could not read shows their hours without a percentage or line, apart from the dashed line of a week with paused work, with Capacity unknown beside their name and in the cell descriptions. Their row stays in its place until their details arrive.
The line is blue for ordinary load, yellow at 90–100% and red over 100%. Only the line changes color, never the figure. 100% fills that person's planning time, which already excludes time reserved for meetings and other overhead. Accessible cell descriptions include the underlying hours and capacity, such as 16 / 30 h, and say under 0.1 for hours too few to show.
A task counts toward its owner's load. In Review tasks with reviewers count toward the reviewer. Paused tasks contribute no hours, but in their planned weeks the line is dashed, also in a full week and in a week with no other load. Resuming restores their hours. Agent rows show hours only, with no percentage, line or over-capacity warning, apart from the dashed line of a week with paused work.
All projects / This project chooses which visible projects contribute hours. The toggle is absent in My view. Use the three layout buttons to expand Team, show it with the Roadmap, or collapse it. Expanded Team keeps the timeline's dates and window controls, and a project's milestones. In My view, whose milestones sit on the rows, it shows none.
Click a person or weekly cell to highlight their tasks. Hover or keyboard-focus a cell to highlight its person and week. Clicking locks the week highlight; click another week to move it. Click the selected person's name again, press Esc, or click outside Team to clear the selection and week lock.
Roadmap filter controls let you keep the selection while adjusting filters. If a filter hides the person, their highlights disappear. Changing scope, date window or layout clears the week lock. Team also lists a person whose tasks in the window all sit under collapsed projects or sub-projects, or are Done tasks that Hide Done in Roadmap hides. Selecting them dims no rows until one of their tasks shows a row, for example when you expand its sub-project.
Qivo spreads each task's remaining hours evenly from its measurement week, or planned start if later, through its planned end. An estimate saved after the planned end counts in the save week. These figures update while you drag bars; there is no separate allocation to enter.
Team utilization shows the plan, so a week can read over 100%. Delay verdicts go further: in an overbooked week each of the person's tasks gets the same share of the hours it asks for that week, and the rest moves to later weeks, so the projected finishes show where an overbooked plan ends up (How the projection works). For example, with 16 hours in a week and tasks that ask for 24 and 8 hours, each gets half its ask, 12 and 4 hours, not 8 each.
Team sync#
Team sync reviews open work one person at a time. Update estimates, status and owners, check delays, and see what each person finished since their last sync. Changes save on the tasks. Use task comments for meeting notes.
Open Team sync in the sidebar or Sync in the phone's bottom navigation. If you left a meeting without the last Done, for example through a row's Board link, the sidebar row and the Sync tab open it again on the step you left. The page belongs to your current organization. Its scope and each step have shareable addresses. Browser Back leaves the page; it does not step through the meeting. Escape does not close the page. Task windows open over it.
Rows update live as participants make changes. Qivo reads each meeting
from the server, so the page opens without loading every task. While its
browser tab or desktop window is hidden or minimized it stops updating, and
when you return it asks again, showing the meeting it had meanwhile. On a
phone, Sync or a plain …/sync link opens your own page if you own work
in scope, once you have chosen a scope. A link naming a step opens that step;
a scoped link without a step opens the team summary.
Scope. The scope you pick is saved with your account:
- All projects includes visible projects in your organization, excluding projects shared from another organization.
- A team includes projects shared with that team and only its members.
- A project includes the project and its sub-projects. A link can also select one sub-project.
The scope menu lists All projects, your organization's teams 25 at a time with a search and Load more, and its top-level projects the same way, 25 at a time with a search and Load more. When a scope is too large to show, the page's notes offer smaller ones: your own teams and your organization's projects for All projects, the projects shared with a team for that team, and a project's sub-projects for a project.
The first time, and when a saved or linked team or project is no longer available to you, the page asks you to choose a team or project. All projects is one of the choices, and Qivo never chooses it for you. A project link says Qivo is opening the project while it checks that you can open it. If that check fails or cannot finish, the page says so with Retry instead of asking you to choose. When you can see no project of your organization, the page says so and who can give you access. If you also belong to another organization, it names the organization the page covers.
Limits. A meeting holds at most 1,000 tasks, counting each once among its open tasks, the Backlog tasks Needs an owner lists and the tasks people finished since their last sync (Limits). Past it the page says "This selection exceeds Team sync's 1,000-task limit." and asks you to choose a smaller team or project. A meeting the server cannot read within its limits says "This selection could not be loaded within Team sync's limits." Neither shows part of a meeting. Both offer the smaller teams or projects you can choose, and a sub-project past them offers its Board. A meeting that grows past its limits while it is open stays as it last fitted, marked as no longer updating since a given time, and keeps what you typed. Its Remaining, status, pause and owner controls, on people's pages and in the team summary, are off until the meeting fits again, an owner list, status menu or reviewer picker that was open closes, and @ mentions still send.
The people list starts with the team summary, then people by name, then agents. It includes owners of To Do, In Progress or In Review tasks without subtasks. The owner is the assignee, or the reviewer for In Review tasks with one. Inactive people remain listed while they own open work. Backlog tasks are excluded from people's pages.
The team summary shows how many tasks are overdue, projected to miss their due date, behind plan, blocked and paused, plus upcoming milestones. The Projected to miss and Behind plan counts include only projects with delay tracking. Where Qivo could not read someone's other work, they read unknown, never 0, and the sentence above them says Qivo could not work out every projected delay. It also lists people at 90% or more capacity this week, and says for how many people the load is unknown where Qivo could not read it, and milestones for this week and next.
The summary reads the next milestone and the milestones of this week and next from the server, for the top-level projects of the scope, and shows them as loading meanwhile. It says "None scheduled" or "No milestones this week or next" only when the server read every milestone. When it could not read them all, the next milestone shows as unknown and the list says some may be missing. If loading the next milestone or the list fails, the summary says so with Retry, and if Qivo refuses to read them, it gives the reason, keeping what it showed until a fresh answer arrives. A scope of more than 200 top-level projects reads none and says so; choose a team or a project instead.
Two lists help complete assignments:
- Needs an owner includes unassigned To Do, In Progress or In Review tasks that are Urgent or High priority, or planned to start this week or earlier. It also includes unassigned tasks due within two weeks or overdue, including Backlog but excluding Done. Tasks with subtasks are excluded. Use Assign to choose an eligible owner from a list of the people who can take the task, 25 at a time with a search and Load more.
- Needs a reviewer includes In Review tasks without a reviewer, longest waiting first. Use Reviewer to assign one.
In a very long list, rows below the first screen appear in the first moments after the opening shows, in shaded space; searching the page or printing loads them all first.
Assigning someone removes the task from the list and places open work on the new owner's page. Task titles open the task window.
A person's page shows this week's load across the organization, regardless of sync scope. For organization admins and users, this includes hidden-project hours and can exceed the Team strip's visible-project total, and changes you make on the page count at once. Organization viewers see the load of the person on screen from the projects they can see, which shows … while it loads and unknown where Qivo cannot read it. For them the team summary's capacity list says the load is unknown, and its Projected to miss and Behind plan counts read unknown wherever they need someone's other work.
The page has three columns, which stack on phones:
- Done since lists tasks without subtasks completed since the person's last sync, or moved to another sub-project while Done since then, newest first. It includes their own tasks and tasks they reviewed from In Review to Done, marked reviewed. Being named reviewer without that status transition does not give review credit.
- On it lists In Progress, then In Review. Reviews appear under the reviewer, marked with the assignee's name. Tasks awaiting an unnamed reviewer stay with the assignee and show no reviewer. Waiting on review lists the person's tasks held by other reviewers, longest waiting first. These rows are read-only apart from the @ comment action and do not count toward the reviewed total.
- Next lists To Do tasks planned to start this week or earlier, or unplanned and due by this week's end. Later, closed by default, holds the remaining To Do tasks.
Within groups, tasks without estimates come first, then planned tasks by start week, then due date, then task number. Undated tasks come last for each date sort.
Rows show the title, task ID, sub-project, plan and due date, with delay or pause marks when applicable. A row says Delay unknown where Qivo could not read its owner's other work. They also flag no estimate, no reviewer and visible unfinished blockers.
Time marks use the person's last sync. untouched since means nobody has edited an In Progress task or commented on it since then. Adding or removing a label, link or attachment is not an edit. Review rows show handed to you for a new hand-off, or waiting since for an older one that nobody has edited or commented on since the hand-off. Entering In Review or changing the reviewer starts a hand-off; changing Remaining does not. Other rows can show the latest status change or comment. After a task moves to another sub-project, it shows no status change until its status changes again. Its hand-off and the time it became Done start again at the move, for the task and each subtask that moves with it, while its Remaining measurement stays. In Team sync a moved review shows handed to you on the move day, although Qivo sends no new Ready for your review message, and a moved Done task appears in Done since again.
Time marks need each task's latest comment, which Qivo checks for every person the page shows. If Qivo cannot check all of one person's open tasks at once, some of their rows show no time mark, and the page says so below the rows.
A review has no recorded hand-off if it was handed over before Qivo recorded hand-offs, or if it has had subtasks since the hand-off. Such a review shows no hand-off age and no handed to you or waiting since mark, and sorts last in Waiting on review and Needs a reviewer. Time marks appear after the task's latest comment loads.
Use the row controls to change tasks without opening them:
- Remaining saves on Enter or leaving the field. Changing steps or leaving the page also saves the focused field and refreshes the projection.
- Status includes all five statuses and Pause / Resume. Done moves the task to Done since; Backlog removes it from the review. Entering In Review applies review time (Review time) and transfers ownership to a named reviewer. If none is assigned, the reviewer picker opens; you can dismiss it without choosing. Leaving In Review returns ownership to the assignee.
- Owner changes the assignee, or the reviewer for an In Review task with one. Its list shows the people who can take the task, 25 at a time with a search and Load more, after Unassigned or No reviewer and the current owner, as the task window's Assignee does (The details column). The task moves to their page and workload figures update.
- @ posts a comment mentioning an active person who can see the task. Its window lists the people who can see the task, 25 at a time with a search and Load more. Pick someone, write a note and press Send. It starts with the assignee chosen on a reviewer's row, or the reviewer on a Waiting on review row, once Qivo has checked that they can still be mentioned. When you press Send, Qivo checks the person again. If they can no longer be mentioned, nothing is posted, your note stays and the window asks you to pick someone else. The recipient gets an Inbox notification (Your inbox). The window closes once the comment is saved, and the note cannot change while Qivo saves it. If Qivo refuses it, for example after you lose edit access, your note stays in the window, also if you closed it meanwhile.
- Board / Roadmap opens the task there. The rows of On it and Next, Later included, have these controls. Done since and Waiting on review rows have neither, and their title opens the task window. Board opens its task window and shows its card behind it, scrolled into view and ringed until a moment after the window closes (Showing a task on the Board). Roadmap finds its bar or unplanned row without starting a planning session. If the task has become Done since its row was drawn, for example in a meeting that no longer updates, and Hide Done in Roadmap is on, the Roadmap shows no row for it. Where it can tell that the task is Done, it says that Done tasks are hidden and where to turn the setting off (The Roadmap). Otherwise, as for a Done task without dates whose row still showed it open, it says that the task is not on the roadmap any more.
- The review tick marks the task reviewed without changing it.
A row's Board and Roadmap links open the task's sub-project. The links beside a person's name filter to that person, using the selected project when applicable; for an all-project or team sync they open the project list with that person's filter kept and a line saying whose tasks a pick will show, and the project you choose opens on the Board or the Roadmap filtered to them, on a phone in its task list. Other filters clear so tasks remain visible; Focus stays unchanged.
Read-only projects disable edits and mentions. On phones, Back closes an open menu or picker before leaving Team sync.
Review progress. Row changes also mark a task reviewed. The footer counts reviewed rows across people and agents, excluding Done since and Waiting on review. A portrait gets a checkmark when all its rows are reviewed, once every task of the meeting has loaded. Use Previous, Next or the people list to navigate. The last Done button returns to where you opened Team sync. Review ticks, open Later lists and expanded agents last until that Done, also while you visit other pages. The next Team sync starts without them, as it does after 30 minutes without using Qivo (Pages stay as you left them).
Agents share a final page. Each summary shows this week's scheduled hours, current and next tasks, and delay counts. Expand an agent for the same task columns and controls. Selecting an agent in the people list expands it.
Last sync. Each person has one shared sync time per organization. Changing Remaining, status, pause, owner or a mention from their page updates it for that person, regardless of who makes the change. Review ticks and assignments from the team summary do not update it.
The time reference for Done since and other marks follows these rules:
- Before a person's first sync, it is the start of the previous working day. Working days are the five days from the organization's week start (Organization settings). With Monday-start weeks, Monday and weekends refer to Friday; Tuesday refers to Monday. The first sync keeps this reference even past midnight.
- Changes less than six hours apart belong to the same sync. Its time reference stays fixed during the meeting on every participant's screen.
- After six hours without a change to that person, the next sync refers to their previous sync's final change.
Last sync in the header shows the latest completed sync. It stays absent until the person has completed one.
Use the Roadmap to reschedule tasks. Team sync has no dragging or auto-fit.